The IESO has released its Draft Medium-Term RFP: Here are the key points

On November 2, 2021, Ontario’s Independent Electricity System Operator (“IESO”) posted a draft of its Medium-Term RFP (the “Draft RFP”) under its Resource Adequacy Framework.

The Draft RFP sets out the process and criteria by which the IESO proposes to procure up to 750 MW of capacity from existing generating or storage resources via three-year commitments beginning in May 2026 (with optional two-year extensions).

The RFP in context

The Draft RFP forms part of a broader Resource Adequacy Framework under which the IESO aims to address a capacity need in Ontario set to emerge in the mid-2020s. The forecasted capacity gap arises from a combination of factors, most notably the retirement of the Pickering nuclear plant, the refurbishment of other nuclear generating units, and expiring generation contracts for certain existing facilities.

In contrast with the pending Long-Term RFP (stakeholdering to begin in 2022) which will aim to procure at least 1,000 MW of new and incremental capacity from both existing and new-build resources that can enter service between 2026-2028 for a seven- to ten-year period, the Draft RFP is geared toward addressing a specific forecasted capacity need limited primarily to already connected resources with or without expiring contracts.

What’s in the Draft RFP?

The full text of the Draft RFP is available here. Key requirements, deadlines, and evaluation criteria include the following (bold terms are defined in the Draft RFP):

Eligibility

Proponents must be “Qualified Applicants” as defined in the Draft RFP, which (among other things) means that Proponents must own an existing and operating generation or storage facility.

The facility must be:

  • capable of delivering services in accordance with the “Medium-Term Capacity Contract” (discussed below);
  • connected to the Ontario grid as of the proposal submission deadline; and
  • currently or previously the subject of an IESO contract that has expired or will expire by April 30, 2026, or is otherwise registered with the IESO and not under contract.

A “Qualified Facility” may include a connected facility, embedded generation facility, embedded electricity storage facility, or an embedded non-market participant facility (as defined in the Market Rules).

Contract Terms

The Medium-Term Capacity Contract will pay suppliers a fixed monthly capacity payment.

Successful Qualified Facilities will enter into contracts containing either:

  • must-offer obligations, which require Qualified Facilities that are non-variable generation to offer into the day-ahead market during qualifying hours at a specified minimum quantity; or
  • facility capacity factor obligations, which require Qualified Facilities to produce a minimum amount of metered generation during qualifying hours.

Process

The Draft RFP includes the following milestones:

  • January 31, 2022: IESO’s deadline for releasing the final RFP and contract;
  • February 21, 2022: Proponents’ deadline for registration; and
  • April 28, 2022: Proposal submission deadline.

The Draft RFP includes additional process guidelines and technical submission requirements, including registration, scope of potential addenda, scope of permissible communication, and post-selection processes.

Evaluation

Proposals will be evaluated in four stages:

  1. Completeness (pass/fail);
  2. Mandatory criteria – the proponent must be a Qualified Applicant, with a Qualified Facility with an accurate nameplate capacity;
  3. Rated criteria scoring – proposals will receive a maximum of 11 rated criteria points across the categories of (i) location; (ii) dispatchability; (iii) operating reserve; and (iv) duration; and
  4. Proposals that are below the “Reserve Price” will have their “Proposal Price” evaluated using the criteria in step 3 to determine their “Evaluated Proposal Price”, which are then ranked.

 

The bigger picture

As the federal government and industry participants become increasingly focused on achieving net-zero, it is notable that the Draft RFP lacks any mandatory scoring or criteria related to emissions reduction. This reflects a continued need for clear guidance and direction from provincial government to the relevant agencies, including the IESO and Ontario Energy Board, on expectations and timelines for achieving net-zero in the electricity sector.

Although the Ministry of Energy has directed the IESO to, among other things, “develop an achievable pathway to zero emissions in the electricity sector” and to submit a report on same by November 2022, the authors submit that this timeline is too long and that clearer emissions-related procurement targets need to be established sooner.

By explicitly including storage alongside generation in the Draft RFP, the IESO does appear to be recognizing stakeholder input concerning the potential of storage resources to further decarbonize the Ontario grid, while boosting flexibility and maintaining efficiency and cost effectiveness.

Notwithstanding, there is arguably an opportunity to further integrate emissions-related criteria in the Medium-Term (and Long-Term) RFP. This need is particularly imminent given the potential for significant increased electricity demand in Ontario resulting from possible future broad based transport electrification and natural gas phase-out.

We’re here to help

Our team at McCarthy Tétrault continues to closely follow the development of the Medium-Term RFP, as well as the IESO’s Resource Adequacy Framework generally. If you would like more information about electricity regulation in Ontario, we are here to help.

Please contact Reena GoyalWill Horne, or any other member of the Power Group at McCarthy Tétrault with any questions or for assistance.

Authors

Subscribe

Stay Connected

Get the latest posts from this blog

[form_control_error]
Please enter a valid email address